best magento templates for your store designed by zingthemes.com, vietnam visa services, vietnam visa home, vietnam visa trip, magento templates, best magento templates for your store, bestmagento templates, 2 cong ty bao ve, 2 dich vu bao ve, 2 bao ve, thoi trang, thoi trang, website chinh phu viet nam, cong thong tin chinh phu viet nam gia vang hom nay, web design blog tin tuc, suc khoe doi song, tin tuc moi online, tin moi 360, tin tuc online, giai tri 24h thiet ke website, thu thuat cong nghe, thoi bao cong nghe, dien thoai sky gia re, magento themes, euthemes.com, themetalent.com, wpdance.com

Vantage Goldfields

Youtube Corporate video

Corporate Video: Operations

Brownfields
Worcester Project PDF  | Print |  E-mail

Worcester Mine Project

A pre-feasibility study was completed on the Worcester Project to determine the economic viability of mining the Mineral Resources delineated to date below the old mine workings.
The study investigated the viability of applying low cost, bulk mining methods to the Indicated Mineral Resources situated between 210m and 560m below surface. The steeply dipping Worcester mineralised zone, which contains free-milling gold, is amenable to mechanised mining by means of continuous retreat open-stoping.  

Based on the mine design, and after applying appropriate economic and modifying factors, an Ore Reserve of some 1.4 million tonnes at a grade of 3.01 g/t (equivalent to 133,000 oz) can be mined over 10 years at a production rate of 150,000 tonnes per year.

Although results of the pre-feasibility study indicate that the project has an IRR of 24%, the proposed mining operation is not regarded as being sufficiently robust to justify a more detailed engineering study at this stage. Instead, the exploration program in and around the Worcester Project area continues to concentrate on delineating additional Mineral Resources in an attempt to provide economies of scale to the project.

 
Crown Project PDF  | Print |  E-mail

Results of a geological modeling exercise of the Mineral Resources at the Crown Prospect, located within the Barbrook Mines Complex, indicated the potential to bulk mine an array of mineralized shears, both in the oxidised zone and from underground.

A scoping study was completed in 2011, which evaluated the viability of open pit mining of oxides and processing them on site. The study was based on the concept of delineating sufficient oxide ore to justify installing a mobile gravity concentrator. This necessitated a reverse circulation (RC) infill drilling program as well as metallurgical test work to ascertain whether the ore is amenable to gravity concentration.

A total of 4051 meters in nineteen RC boreholes were drilled into the area above 4 Level, which is approximately 150m below surface. The objective of the drilling program was to define the oxide/sulphide interface and to enhance the definition of the potentially bulk mineable Mineral Resources.

After incorporating the RC drilling results into the existing drill core sampling data base, a revised block model was completed for the area above 4 level, which indicated an upgrading of the Mineral Resources to 1.777 Mt @ 2.65 g/t or 151,000 oz (at a 1.0 g/t cut-off). These Mineral Resources include oxide, transitional zone and sulphide material. They are in addition to the Mineral Resources previously defined for conventional, selective mining below 4 level. Collectively, the total Mineral Resources at Crown amount to 2.12 Mt @ 3.14g/t.

Unfortunately, the metallurgical results were disappointing in that the concentrating test work indicated that it is not feasible to process the oxide portion of the Mineral Resources using a mobile gravity concentrating plant. Consequently, the scoping study has shown that it is not economically viability to treat only oxide material by open mining methods using a processing option which does not require significant capital expenditure. Other alternatives for mining the sulphide material from underground and treating it at the Central Metallurgical Complex will be investigated during the Barbrook Stage 2 investigations.